50 Bridge Street

Type Commercial
Client AMP
Location 50 Bridge St Sydney
Completion Date 2006

The Project Brief

The refurbishment of AMP’s 45 storey, 65,000m2 building was carried out over a number of stages and with multiple contracts, consistent with tenant relocations and market requirements. This major transformation of the 1970’s building, including extended lower floor plates and reconfigured foyer, was completed in 1993, with other works continuing till 2006.

Jeff Saunders was the contract administrator for these works and the project manager responsible for the majority of on floor refurbishment work as well as major services upgrade works carried out between 1990 and 2006. Typical floor works included new amenities and new office area finishes and building services throughout.

The works program also included significant tenancy co-ordination for relocating and incoming tenants throughout the building.

The Challenges

Separate works contracts included new BMCS and security services, lift refurbishment as well as whole of building fire service sub duct installation through occupied tenancies, required detailed planning and coordination.

The Project Outcome

The project was completed in 2006 to the satisfaction of AMP who continued the services of Jeff, concurrently on other projects.